Major Mining Equipment Selected and
Ordered for Ruby Creek Project
Friday, September 28th 2007 - Vancouver, British Columbia (MOLY @ 35.00US/lb)
Adanac Molybdenum Corporation (TSX:
AUA) (Pink Sheets: AUAYF) (Frank: A9N) is pleased to announce letters of award
have been issued to four Canadian companies for the supply of major items of
mining equipment for the Ruby Creek Molybdenum Project, situated near Atlin,
B.C.
The suppliers and equipment to
be provided are as follows:
• Transwest
Mining Systems will supply a PC4000 hydraulic shovel with spare bucket and
spare truck body and six HD1500 haul trucks (200 tonne capacity);
• Finning
(Canada)
Ltd. will provide two Caterpillar 16M motor graders;
• Coneco
Canada Ltd. has been selected to supply three wheel loaders (WA500, WA600 and
WA900L), one excavator (PC300 HD) and two bulldozers (D375); and
• Atlas Copco Canada Ltd. will provide one diesel-powered rotary
drill (PV271), together with drill string and rotary bits.
The value of the machinery is almost $23 million, bringing the total
value of equipment purchased to $93 million. The items are scheduled to be
onsite by the summer of 2008.
“The equipment being ordered now represents another major step
toward the commencement of construction of our open-pit molybdenum mine,”
said Michael MacLeod, President & Chief Executive
Officer of Adanac.
The action follows the awarding of an Environmental Assessment
Certificate for the project from the British
Columbia government on September 10, 2007. The clearance
was given following extensive consultations with the Taku River Tlingit First
Nation and the community of Atlin.
Federal agencies were fully involved in the environmental review
process, and approval through the Department of Fisheries and Oceans is
expected before the end of October.
Specific permit applications to upgrade the existing access road are
under review by provincial regulatory agencies, with field work to begin
immediately upon receipt of approvals.
Road work is scheduled to start in early October and site preparation
will follow shortly afterward. Construction will continue through the winter of
2007-2008. Start up and commissioning of the 20,000 tonne/day concentrator is
scheduled for the first quarter of 2009.
On Behalf of Management
ADANAC
MOLYBDENUM CORPORATION
Michael
MacLeod,
President & Chief Executive Officer