Need A Printable Format? Click Here!
EXECUTIVE SUMMARY - THE RUBY CREEK PROJECT- A CLEAN PORPHYRY MOLYBDENITE RESOURCE
April 12, 2006 - Vancouver, British Columbia
Mr. Larry W. Reaugh, President & CEO, Adanac Moly Corp. (TSX.V: AUA, Frank: A9N) ("Adanac"), is
pleased to report the results of the Ruby Creek Molybdenum feasibility are positive and Wardrop
Engineering Inc. recommends continuing development through detailed engineering, which is set
to commence during the second quarter of 2006.
MEASURED & INDICATED TONNES 206,375,000 @ 0.063% Mo
OPEN PIT MINING & MILLING 20,000 TONNES/DAY FOR 20+ YEARS
Mineable reserves are 113,400,000 tonnes grading .066% Mo of proven and probable ore. Stockpiled
proven and probable reserves totaling 31,300,000 tonnes grading .034% Mo will be available as
mill feed at the end of the open pit mine life.
MOLYBDENUM PRODUCTION
First 5 YEARS 58,341,000 lbs Mo
Average grade of Molybdenum (1st 5 years)
*CAPITAL COSTS $434,400,000 ±15%
* includes preproduction capital, now shown as a
capital expense rather than an operating expense.
OPERATING COSTS
First 5 YEARS $5.87US/lb Mo
All dollars are in Canadian funds unless otherwise noted
PROJECT SUMMARY
Mine Life: 21 years
Milling Rate: 20,000 tonnes per day
Strip Ratio: 0.95 (waste)/1.0 (ore)
Tonnage milled: 143.7 million tonnes, average grade 0.059% Mo
Average Recovery: 89%
Molybdenum in concentrate: 75.9 million kilograms (167.4 million pounds)
Base Case: IRR 24.42%, NPV @ 8% = $222.2 Million, Payback = 3.1 Years
The Company is proceeding with the Engineering Study on the High Pressure Grinding Rolls (HPGR)
through Wardrop Engineering. It is expected that the concentrator will incorporate the HPGR
system instead of the base case SAG Mill design. This aspect alone will increase the IRR to
28.85%, NPV to $305,100,000 and payback period reduced to 2.9 years.
Diamond drilling within the pit to begin in June for metallurgical samples, will also
incorporate angle holes over the high grade portion of the open pit. The purpose of drilling
the angle holes is to penetrate the vertical mineralized fractures (not encountered in vertical
holes) which were picked up on the 10,000 tonne bulk testing in 1970.
A sensitivity on the project economics was carried out to determine the impact of a potential
15% increase in the grade of ore. The case for considering potential increase in grade is based
on detailed drill hole bulk sampling studies described in Kaiser Engineers, "Feasibility Study
of the ADANAC Molybdenum Project" prepared for Kerr Addison Mines Ltd., Report No. 71-1,
(January 1971). While this work is not NI43-101 compliant, the results from bulk sampling
indicated higher grades than the drill program by as much as 20%. For the purpose of the
sensitivity study only a grade increase of +15% was assumed. The project IRR increases to
35.03% and the NPV increases to C$405 million at an 8% discount.
MOLYBDENUM OUTLOOK
At a conservative long term demand growth projection of 2%, an additional 3.5 million kgs Mo
(7 million lbs Mo) per annum will be required to meet demand. If growth in demand continues at
the current rate of 3% per annum the annual additional quantity required becomes 4.5 million kg
Mo (10 million lbs Mo) and 7.5 million kg Mo (16 million lbs Mo) at 5% annual growth rate.
There is clearly a need for additional mine output. In a report for AIM-listed International
Molybdenum PLC issued in July 2005, consultant CRU Strategies estimated that global moly
supplies would total under 350 million lbs in 2005 but be in deficit by between 6 and 26
million lbs on base case and upper case scenarios by 2009.
This press release is reviewed by John W. Fisher, C.Eng., P.Eng., an independent qualified
person as defined by NI43-101. Mr. Fisher visited the Ruby Creek property on June 21, 2005.
On Behalf of Management
ADANAC MOLY CORP.
Larry W. Reaugh,
President and Chief Executive Officer
The TSX-Venture Exchange has not reviewed and does not accept responsibility for the adequacy
or accuracy of this release. This news release may contain certain "Forward-Looking Statements"
within the meaning of Section 21E of the United States Securities Exchange Act of 1934, as
amended. All statements, other than statements of historical fact, included herein are
forward-looking statements that involve various risks and uncertainties. There can be no
assurance that such statements will prove to be accurate, and actual results and future events
could differ materially from those anticipated in such statements. Important factors that could
cause actual results to differ materially from the Company's expectations are disclosed in the
Company's documents filed from time to time with the Toronto Venture Exchange, the British
Columbia Securities Commission and the US Securities and Exchange Commission.
Adanac Moly Corp.
2A 15782 Marine Drive, White Rock, BC CANADA V4B 1E6
Telephone: 604-531-9639 Facsimile: 604-531-9634
Email: info@adanacmoly.com
Visit www.AdanacMoly.com for more information
|