FOR IMMEDIATE RELEASE
ADANAC RUBY CREEK MOLYBDENUM PROJECT REVIEW
January 16, 2007 -
Vancouver, British Columbia
Adanac Molybdenum
Corporation (“Adanac”)
(TSX.V: AUA, Pink Sheets: ANCGF, Frank: A9N) reports on recent events and a
historical review of the Project situated 24 kilometers Northeast of Atlin, BC.
Historical Review:
The Ruby Creek property was acquired
thru staking the claims in 2000.
The occurrence of molybdenum on the property was first discovered in
1905 but serious and systematic development didn’t get underway until the
1960’s. Major Canadian
companies (Kerr Addison Mines Ltd. and Placer Developments Ltd.) explored the
property extensively and each completed feasibilities but neither proceeded to
production on account of low molybdenum prices.
Adanac Gold Corp. (now Adanac
Molybdenum Corporation) continued exploration to provide, along with much of
the earlier exploration work, a sufficient and reliable basis to establish the
molybdenum resource which met the most recent tight standards demanded by
regulatory authorities – the National Instrument Policy 43-101. This was achieved in April 2005. On-going exploration in 2004, 2005 and
2006 has provided additional data; the 2006 results are currently providing the
most up to date basis for Golder Associates to revise their earlier resource
estimate (2005) which is shown below.
Based on a 0.04% Mo cut off the
reserves are:
|
Proven
tonnes
|
38.9 million at 0.077% Mo
1.2
million at 0.0.035% Mo (stockpile)
|
|
Probable
tonnes
|
73.5 million at 0.060% Mo
30.1 million at 0.034% Mo
(stockpile)
|
|
Total tonnes
|
143.7 million at 0.059% Mo
|
Ruby Creek
Project Summary
|
Mine
Life:
|
21 years
|
|
Milling
Rate:
|
20,000 tonnes per day
|
|
Strip
Ratio:
|
0.95 (waste) /1.0 (ore)
|
|
Proven
and Probable ore is:
|
113.4 million tonnes @ 0.066% Mo
30.3 million tonnes @ 0.034% Mo
|
|
Ore grade first 5 years:
|
0.084% Mo
|
|
Mill
recovery:
|
89%
|
|
Molybdenum
in concentrate:
|
75.9
million kilograms (167.4 million lbs.)
|
|
Preproduction
capital ($Cdn):
|
$434.4
million
|
|
Average
Operating Cost (first 5 years):
|
$5.87
US/lb/. Mo
|
|
Base
Case:
|
IRR=24.42%,
NPV @ 8%=$222.2 million
Payback
= 3.1 years
|
|
With
incorporation of the high pressure grinding rolls the economics are improved:
|
IRR=28.85%
NPV @ 8% = $305.1 million
Capital
Payback – 2.9 years
|
Adanac has the following advantages over the predecessor
companies:
·
Adanac
has a 100% interest in the property, whereas the original property was burdened
by a 3.5% NSR to Johns Manville. Kerr Addison, could only earn a 60% interest
and Placer a 70% interest.
Adanac Molybdenum Corporation
Press Release - January 16, 2007
Page 2
·
The
price of molybdenum is 14 times the price at which Kerr Addison undertook
feasibility work in 1970 and 4 times the price when Placer undertook its
feasibility studies.
·
Multi-billion
dollar long-term contracts are being entered into by Chinese corporations for
the supply of iron ore which bodes well for a long sustained demand for
molybdenum due to its extensive use in stainless steel and other steel
products. Indications are for a steadily increasing demand for molybdenum.
·
Currently
surplus power is available from the Yukon Grid which would require the company
to install only 100 kilometers of transmission line. Yukon power was not available in the
1970’s and 1980’s.
·
Road
access to Skagway, Alaska’s deep water port is now
available.
With the resource established
(April 2005) the Company moved with speed to develop a preliminary
feasibility. The basis was set at
20,000 tonnes per day mill throughput and, to eliminate probable delay
associated with having to permit an overland hydro line for 100 kms where none
existed (in addition to permitting an upgraded line on approx 150 kms existing
line). The basis includes provision
for electrical power, in the first 3 – 5 years, from diesel generators.
The preliminary feasibility was
completed in a five month period (April – September 2005). The recommendations to proceed with full
bankable feasibility was acted on immediately and this was completed April 2006
with recommendation to study the applicability of High Pressure Grinding Rolls
(HPGR) technology as an alternate to conventional Sag Mill technology. This study indicated significant benefits
for the project thru more energy efficient crushing/grinding. It is now included in the updated
bankable feasibility.
2007 Projection:
·
Detailed
engineering is priority. As this
work moves forward the procurement of “long lead time“ major pieces
of plant/infrastructure is critical to maintaining the aggressive schedule to
complete construction by end of 2008.
·
A
production decision will be made in the first quarter.
·
Receipt
of Mining & Environmental Permits are slated for end of first quarter
·
Start
of construction is expected by mid-year when winter precipitation is clear of
the property.
·
Major
financing is expected to be structured and completed in the second quarter.
·
An
Impacts Benefit Agreement (IBA) for Taku River Tlingit First Nations is to be
completed in the second quarter of the year.
·
Approximately
1.5 kg of high grade Molybdenite concentrate product has been produced for
samples to potential end users.
·
This
year’s exploration programme will include further work to test the new
zone of molybdenum mineralization discovered to the southwest in the 2006 field
work.
·
An
independent review of the geotechnical basis for the tailings impoundment,
waste dumps & site water management has been completed and finds no
significant errors/flaws in the feasibility work completed.
2006 Summary:
·
Currently,
the Company has contracted with Amec Americas Ltd., (AMEC) to provide the
detailed engineering and procurement services for the Ruby Creek Project. The contract is expected to be completed
in 13 months.
·
As
well, the Company is expanding the Adanac management team starting with the
employment of Rick Alexander, P. Eng., as Vice President of Project
Development, and expects to hire several more key professionals in the next few
months. This will insure Adanac has
the experience and capabilities to build and operate the 20,000 TPD
Project. This is in addition to
adding expertise in engineering design, feasibility, financing, construction
and mining operations to the Board of Directors over the past 12 months.
Adanac Molybdenum
Corporation
Press Release - January 16, 2007
Page 3
·
Over
the past six months G & T Metallurgical Laboratory of Kamloops, BC has
completed testing and concentration of over 2,116 kgs. of material from the
2004, 2005 vertical and 2006 angle hole drill programs to produce a concentrate
suitable for testing by potential strategic partners in the Ruby Creek
Project. Results from the 2006
metallurgical testing program will be available shortly. The Company has had several meetings
with potential strategic partners, funds and banks regarding possible strategic
partnerships, joint ventures partnerships, debt and equity financings. This process is ongoing.
·
2,668
metres of angle drilling was completed in thirteen holes in the high grade pit
area. Grade and continuity appear to be much
better than the results from the previous vertical drill hole programs. Golder Associates is currently
completing a statistical NI 43-101 grade study in the high grade pit area (5
year pit averaging .084% Mo) which is expected in the next 6 weeks. Total holes and meters drilled on the
Ruby Creek Molybdenum Project since 1969 are 49,786 meters (163,300 ft.) in 283
drill holes. This year’s
exploration included 1,333 meters of diamond drilling in 3 holes to the west
and southwest of the existing open pit plan. This indicates a new, previously unknown
zone of molybdenum mineralization exists to the southwest. Further work is scheduled for the 2007
exploration program.
·
The
Company successfully completed a financing at $1.02/share for $12,822,210.53
December, 2006.
·
CPM
Group of New York, NY was appointed as Senior Financial
Advisor.
·
Adanac
signed a Phase 2 Collaborative Relationship Memorandum of Agreement with the
Taku River Tlingit First Nation (TRTFN) in October of 2006.
·
Formal
application for the Environmental Assessment Review process was submitted in
August of 2006.
·
Formal
application for the Mining Permit to the Chief Gold Commissioner was submitted
in August 2006.
·
Golder
Associates Ltd. updated The NI43-101 Study whereby resources increased to
206,375,000 tonnes grading .063% Mo at a .04% ore cutoff (285,604,000 lbs.).
·
Completed
the Bankable Feasibility Study (Wardrop Engineering) in April, 2006 and final
Bankable study using HPGR system in July 2006.
·
An
independent review of the process design/infrastructure completed for the
bankable feasibility found no significant errors/flaws in this work.
2005 Summary:
·
The
Company completed 4,984 metres of diamond drilling in 19 holes: the results provided basis for Golder
Associates to revise and update the earlier NI 43-101 resource estimate.
·
In
November, the Company announced a $2,000,000 flow through and $500,000 non-flow
through private placements @ $0.75 and the Company is now listed on the
Frankfurt Exchange (ticker symbol: A9N).
·
Adanac
entered into stage one work plan initiative with the Taku River Tlingit First
Nation in July.
·
Amec
PLC completed NI 43-101 Resource Study reporting 205,000,000 tonnes grading
.062% Mo at a .04% Mo cutoff. Total
moly is 278,100,000 lbs.
·
Pre-feasibility
Awarded – Pre-feasibility work was contracted to the following
engineering firms (These firms continued on with the bankable feasibility
study).
a) GOLDER ASSOCIATES LTD. (GOLDER) – for mine design, rock slope stability,
and updating the resource model to include the diamond drilling just completed.
GOLDER is a world renowned company recognized as a leader in resource and
reserve estimation/evaluation and for its mining and geological expertise.
b) WARDROP ENGINEERING INC. (WARDROP) – for detailed development of the mill
process and infrastructure including the diesel-electric power plant to be used
in the initial years of operation; and to evaluate specific alternative options
for process unit operations. WARDROP is a full service engineering company with
50 years of successful history serving the Canadian mining industry.
Adanac Molybdenum Corporation
Press Release -
January 16, 2007
Page 4
c) MINNOVEX TECHNOLOGIES INC. (MINNOVEX) – for completion of comminution and
flotation test work to optimize these processes for the Ruby Creek resource.
The test work results are essential components for detailed process design, and
the geometallurgical parameters will also be incorporated into GOLDER’s
resource model. MINNOVEX is a recognized leader in comminution & flotation
test work for process plant design and recently became part of the Lakefield
SGS group.
d) KLOHN CRIPPEN CONSULTANTS LTD. (KLOHN CRIPPEN) – continuation of site
geotechnical engineering services for site water management, tailings storage
and waste rock storage. KLOHN CRIPPEN is a recognized leader in the design of
tailings dams.
2004 Summary:
·
Amec
PLC appointed for NI43-101 Resource Study.
·
Adanac
completes 9,022 meters (29,592 ft.) of diamond drilling in 36 holes for the
NI43-101 resource study being completed by Amec PLC. Previously, 31,950 meters
(104,846 ft.) were completed by Placer Development Ltd., Adanac Mining
Exploration Ltd., Kerr Addison mines Ltd., and Climax molybdenum Corporation.
In addition, Kerr Addison completed a program of underground development of
1,116 meters (3,660 ft.) entailing adit access, cross-cutting and raising six
holes to produce 9,545 tonnes of ore for on-site processing in a 100 tonnes/day
pilot mill. Test work in 1971 was to determine mill head recoveries which
averaged 91% and were used in subsequent feasibility studies (three) carried
out by Kerr Addison in 1970, Placer in 1978 and 1979. Head grades from the
milling process showed a 20% increase in grade over the drill hole assays.
·
Klohn
Crippen contracted to initiate environmental and socio-economic studies.
2003 Summary:
·
Adanac
engages DW Phillip Mining to produce an economic evaluation on the Ruby Creek
Molybdenum Project. DW Phillips, P. Eng. Recommend the company to begin
preliminary feasibility studies and obtain a NI43-101 Resource Study. Moly
trading at (US) $6.00/lb.
2001 - 2002 Summary:
·
Adanac
begins acquisition, collection and compilation of all previous geological,
engineering and environmental work.
2000 Summary:
·
Adanac
stakes Ruby Creek Molybdenum deposit.
On Behalf of Management
ADANAC MOLYBDENUM
CORPORATION
“Michael
MacLeod”
Michael MacLeod, President and Chief Executive Officer
The
TSX-Venture Exchange has not reviewed and does not accept responsibility for
the adequacy or accuracy of this release. This news
release may contain certain "Forward-Looking Statements" within the
meaning of Section 21E of the United
States Securities Exchange Act of 1934, as
amended. All statements, other than statements of historical fact, included
herein are forward-looking statements that involve various risks and
uncertainties. There can be no assurance that such statements will prove to be
accurate, and actual results and future events could differ materially from
those anticipated in such statements. Important factors that could cause actual
results to differ materially from the Company's expectations are disclosed in
the Company's documents filed from time to time with the Toronto
Venture Exchange, the British Columbia
Securities Commission and the US
Securities and Exchange Commission.
|


|
Adanac Molybdenum Corporation
2A 15782 Marine Drive,
White Rock, BC CANADA
V4B 1E6
Telephone:
604-531-9639
Facsimile: 604-531-9634
Email: info@adanacmoly.com Visit
www.AdanacMoly.com for more
information
European
Investor Relations contact: Nick Fuller or Samantha Fletcher – Fuller
Fletcher & Associates Ltd. Visit: www.fullerfletcher.com
email: nick@fullerfletcher.com
Tel +44 207 256 5204 Fax +44 207 256 5678
|